Method Statement: Double-Layer SBS Basement Waterproofing

Method statement PS-MS-02: positive-side two-ply PetroGrip SBS basement waterproofing on raft and walls, with PVC waterstops at joints.

This method statement covers positive-side basement waterproofing using two plies of PetroGrip SBS torch-applied membrane under the raft and on external retaining walls, continuous through the raft-to-wall junction, with PVC waterstops as a second line of defence at construction joints.

It includes dewatering conditions, pile-head details, waterstop fixing and welding, protection and backfilling sequence, and the hold points to sign before each cover-up.

Key specifications

Values shown are taken from the published brochure/TDS. Project acceptance follows the approved batch certificate and consultant specification.

Document
PS-MS-02, 4 pages
System
PetroGrip SBS, two plies, positive-side
Laps
Side 100 mm / end 150 mm; plies offset by half a roll width
Raft tails
Both plies project at least 300 mm for lapping to wall membrane
Wall membrane
Carried at least 150 mm above finished ground level
Protection
50 mm screed on raft; protection board on walls before backfill

Applications

  • — Basements under groundwater or hydrostatic pressure
  • — Raft foundations and external retaining walls
  • — Below-grade structures needing redundant protection