Method Statement: Swimming Pool Waterproofing Under Tiles
Method statement PS-MS-03: TERACOO Weather Coat GP cementitious waterproofing of concrete pool shells under tiles, including the fill test.
This method statement covers waterproofing of reinforced concrete swimming pool shells — floor, walls, steps, benches and balance tank — under tile finishes with TERACOO Weather Coat GP, including fitting and joint detailing and the fill test before tiling.
Where polyurea is specified for the pool instead, follow the PETROUREA spray method statement.
Key specifications
Values shown are taken from the published brochure/TDS. Project acceptance follows the approved batch certificate and consultant specification.
- Document
- PS-MS-03, 3 pages
- System
- TERACOO Weather Coat GP, two coats at right angles
- Mix
- 1 : 2 liquid to powder by weight, used within 1 hour
- Substrate
- Pull-off strength > 145 psi, SSD before coating
- Curing
- Wet cure for at least 3 days
- Fill test
- Daily level against evaporation before tiling
Applications
- — Concrete swimming pool shells under tiles
- — Balance tanks and water features
- — Water tanks and wet areas