Method Statement: Torch-Applied Membrane Roof Waterproofing
Method statement PS-MS-01: PetroGrip APP/SBS torch-applied membranes on concrete roofs and podiums, covering priming, laps, upstands and flood test.
This method statement covers waterproofing of concrete roof slabs, terraces and podiums with PetroGrip APP or SBS torch-applied membranes, including single-ply and two-ply systems, upstands, outlets, penetrations, flood testing and protection.
It sets out hold points, acceptance criteria and the records to hand over, so consultants can approve it as a submittal alongside the PetroGrip datasheets.
Key specifications
Values shown are taken from the published brochure/TDS. Project acceptance follows the approved batch certificate and consultant specification.
- Document
- PS-MS-01, 4 pages
- System
- PetroGrip APP / SBS, single or two-ply, torch-applied
- Side / end laps
- Minimum 100 mm / 150 mm, end laps staggered by 300 mm
- Upstands
- At least 150 mm above finished roof level
- Flood test
- About 50 mm depth, at least 48 hours
- Includes
- Hot works safety, inspection and test plan, handover records
Applications
- — Concrete roof slabs and terraces
- — Podiums and trafficked decks under protection
- — Industrial and commercial roofs
Related products
- PetroGrip APP
APP-modified torch membrane—2mm to 4mm with plain, aluminum, or granular surfacing.
- PetroGrip SBS
SBS-modified torch membrane—3mm and 4mm with plain, aluminum, or granular surfacing.